Yard sources said that seven modules for pipe racks were being delivered – SPP305,306,307,308,309,351,352 – carrying a total weight of 2200 tonnes.

The first module has been under pre-erection since last Saturday before it was shipped to a port in Shanghai or Jiangsu province for delivery to material offloading facilities at the project site in the Port of Sabetta .

Sources said that Sinopacific will be only responsible for shipping the modules on a free on board basis to a bulk and cargo intermediate storage yard at Arkhangelsk on Russia’s Arctic coast and then the lead contractor will take the shipping over and ship the modules to Sabetta with ice breaker vessels.